Control Units CU240S
Operating Instructions, 07/2008 - FW 3.2, A5E00766042B AD
45
Commissioning
5
Overview
A G120 inverter is composed of the Power Module and the Control Unit. After snapping the
Control Unit on to the Power Module for the first time, the devices must identify each other.
To indicate, that the Power Module and the Control Unit are not yet identified, F0395 is
displayed. For further information to the message F0395, refer to section "Message F00395".
The G120 inverter provides two options for commissioning:
● Single commissioning
One inverter is parameterized for commissioning with an individual parameter set.
Usually, you use the STARTER or BOP for single commissioning.
● Series commissioning
Several inverters are parameterized for commissioning via download of a complete
parameter set. Usually, you use the MMC for series commissioning.
Note
We recommend commissioning via STARTER. The commissioning process using
STARTER is driven by dialog boxes and will not be interpreted in this manual. This
manual describes the parameter related commissioning via BOP.
Interfaces
The G120 inverter provides different communication interfaces. The following figure provides
you an overview: