Commissioning
5.4 Message F00395
Control Units CU240S
54
Operating Instructions, 07/2008 - FW 3.2, A5E00766042B AD
5.4
Message F00395
Description
The message F00395 is displayed to prompt the user to check the parameter set or to
perform basic commissioning. By confirming F00395 the user accepts responsibility for
setting the parameters correctly. In the case of fail-safe CUs an acceptance test must be
performed.
Note
Acceptance test
An acceptance test means to check and record the inverter functions in accordance with the
"acceptancce log" section in the appendix of this manual.
Cases which require F00395 to be confirmed:
● First power ON
● Automatic download
● Swap of the Control Unit
Note
F00395 does not indicate an inverter fault.
Confirming F00395
F00395 can be confirmed using one of the following methods:
● To accept the current parameter set and save it from RAM to EEPROM one of the
following can be done:
– Press
function key on the BOP
– Quit via digital input or PLC signal (depends on the settings of P0700)
● To not accept the current parameter set one of the following ways can be used:
– Factory reset
– Setting P7844 = 2 (only possible in case of an automatic MMC download at startup)
automatic MMC download will be undone (EEPROM data saved in RAM).
Note
F00395 cannot be acknowledged by using power-cycling.
Confirming F00395 on fail-safe CUs
For CUs with fail-safe functions, it is necessary to do an acceptance test after confirming
F00395. For details of the acceptance test refer to the "Commissioning the Fail-Safe
functions" section in this manual.