3 Mechanical Installation SV800/SV800A User Manual
20
3.2 Installation direction and space
3.2.1 Installation space
The surrounding installation space and clearance should be reserved varies with the power
levels of the SV800 series inverter.
Single inverter installation
Fig.3-1 Single inverter installation
Table 3-2 Installation clearance requirements
Power level
Dimensional requirements (unit: mm)
2.2KW~22KW
A1≥10
B1≥200
C1≥40
30~37KW
A1≥50
B1≥200
C1≥40
≥45KW
A1≥50
B1≥300
C1≥40
Multi-inverter installation
The SV800 series inverter dissipates heat from the bottom to the top. When multiple inverters
work together, please install them side by side and the upper of the inverter should be aligned.
Clearance should be reserved between each inverter as shown in
Fig.3-2
:
C1
A1
A1
B1
B1
(Front View)
(Side View)
Vertical upward
Summary of Contents for SV800 Series
Page 8: ......