7
S a f e t y i n s t r u c t i o n s
V115E_09.20
Series-65H Hoist Pos 2
Keep the instruction and warning signs and
stickers undamaged and readable. If nec-
essary change them!
Only qualified persons well familiar with the
hoist are allowed to carry out service and
maintenance operations.
Secure and protect the service area with
fences and warning signs when necessary
for the occupational safety.
It is not permitted to change the hoist’s con-
structions, to add any supplements or make
other rearrangements without the permis-
sion of the manufacturer or the importer.
This concerns both the design and the in-
stallation of the safety equipment as well
as the welding of the constructions includ-
ing repair welding.
All spare parts must be of equal quality with
the original spare parts and approved by
the manufacturer or the importer of the
hoist. The user is obliged to check the qual-
ity of the spare part prior to its installation.
2.5 Service and Maintenance
If during the service or repair operations any
device or its part connected to the safe-
ty system is removed, it must be reinstalled
and tested immediately after finishing the
service and repair operations!
Operations connected with the electrical
equipment are allowed to carry out only by
qualified professionals in electricity well fa
-
miliar with the equipment’s operation.
Prior to electrical or other service opera-
tions shut off the voltage and secure the
de-energization by locking the main switch.
Put out a warning sign telling that the hoist
is under repair.
Follow the service instructions and service
intervals given in the hoist’s instruction man-
ual.
The hoist is to be inspected in the intervals
prescribed by the law and local regula-
tions. Keep records on the inspections.
When working on the cage roof
and while the hoist is moving
do not hang down or lean out
beyond the railings. Especially
during the upward movement
there is a great risk of collision
or squeezing against the cage
and/or the landing structures.
☞
Carry out one working phase
at a time carefully and always
finish it before starting the next
phase or having a break.
☞
Summary of Contents for 65H Series
Page 2: ...2 T a b l e o f C o n t e n t s Series 65H Hoist Pos 0 V115E_09 20...
Page 10: ...G e n e r a l i n f o r m a t i o n 2 V115E_09 20 Series 65H Hoist Pos 1...
Page 26: ...G e n e r a l i n f o r m a t i o n 18 V115E_09 20 Series 65H Hoist Pos 1 4450 L L1 L2 TWIN...
Page 34: ...G e n e r a l i n f o r m a t i o n 26 V115E_09 20 Series 65H Hoist Pos 1...
Page 36: ...S a f e t y i n s t r u c t i o n s 2 V115E_09 20 Series 65H Hoist Pos 2...
Page 46: ...S a f e t y i n s t r u c t i o n s 12 V115E_09 20 Series 65H Hoist Pos 2 MAX 1000 kg TH_10E...
Page 54: ...S a f e t y i n s t r u c t i o n s 20 V115E_09 20 Series 65H Hoist Pos 2 Tx527...
Page 55: ...21 S a f e t y i n s t r u c t i o n s V115E_09 20 Series 65H Hoist Pos 2...
Page 82: ...O p e r a t i n g i n s t r u c t i o n s 24 V115E_09 20 Series 65H Hoist Pos 3...
Page 84: ...2 V115E_09 20 T r o u b l e s h o o t i n g Series 65H Hoist Pos 4...
Page 124: ...10 V115E_09 20 Service and maintenance Series 65H Hoist Pos 5...
Page 144: ...30 V115E_09 20 Service and maintenance Series 65H Hoist Pos 5 Picture 3c Picture 3b...
Page 154: ...40 V115E_09 20 Service and maintenance Series 65H Hoist Pos 5...
Page 156: ...Inspection forms V115E_09 20 Series 65H Hoist Pos 8 SC HOIST INSPECTION FORMS...
Page 164: ...Inspection forms V115E_09 20 Series 65H Hoist Pos 8 SC HOIST INSPECTION FORMS...