9 Commissioning of on-load tap-changer by transformer manufacturer
Maschinenfabrik Reinhausen GmbH 2015
211
4349315/00 EN
VACUTAP® VR®
2.
Connect the grounding screw of the motor-drive protective housing to
the transformer tank.
Figure 287: Grounding screw on motor-drive unit
3.
When using a temperature sensor, ground the temperature sensor
housing on the on-load tap-changer using the grounding cable.
Performing tests on motor-drive unit
Please contact Maschinenfabrik Reinhausen if any aspect of the tests is not
clear.
Performing function tests
Perform function checks as described in relevant MR operating instructions
"TAPMOTION® ED".
Dielectric tests on transformer wiring
Note the following points for dielectric tests on the transformer wiring:
The motor-drive unit is put through dielectric tests before delivery.
► Before the dielectric test for the transformer wiring, disconnect drive
from the section to be tested to rule out increased component loading
for those components fitted in the motor-drive unit.
Performing trial tap-change operations
Before energizing the transformer, test tap change operations must be car-
ried out to check the mechanical functions of on-load tap-changer and mo-
tor-drive unit.
9.3
9.3.1
9.3.2
9.4
Summary of Contents for VACUTAP VR
Page 1: ...On Load Tap Changer VACUTAP VR Installation and Commissioning Instructions 4349315 00 EN ...
Page 246: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 246 4349315 00 EN VACUTAP VR ...
Page 248: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 248 4349315 00 EN VACUTAP VR ...
Page 266: ......
Page 267: ......