11 Commissioning transformer at installation site
Maschinenfabrik Reinhausen GmbH 2015
217
4349315/00 EN
VACUTAP® VR®
Commissioning transformer at installation site
Before energizing the transformer, check that the motor-drive unit and pro-
tective relay are functioning correctly and fill the on-load tap-changer oil
compartment with new mineral insulating oil. Proceed as follows:
Checking motor-drive unit
Before commissioning the transformer, repeat the function tests on the mo-
tor-drive unit as described in the operating instructions "TAPMOTION® ED".
WARNING
Danger of death or severe injury!
Danger of death or severe injury due to incorrect operation!
► Under no circumstances is the transformer to be commissioned if the
functions are not satisfied in accordance with the Function tests sec-
tion.
NOTICE
Damage to the on-load tap-changer and motor-drive unit!
Damage to on-load tap-changer and motor-drive unit due to condensate in
the motor-drive unit!
► Always keep protective housing of the motor-drive unit tightly closed.
► If the standstill time before commissioning exceeds 8 weeks or opera-
tion is interrupted for longer than 2 weeks, the heater must be connect-
ed and turned on to prevent the condensation of moisture inside the
protective housing. If this is not possible (e.g. during transportation),
place a sufficient amount of dehydrating agent in the protective hous-
ing.
NOTICE
Damage to the on-load tap-changer and motor-drive unit!
Damage to on-load tap-changer and motor-drive unit due to incorrect use of
position transmitter equipment!
► Only circuits stated in the chapter Technical data for position transmitter
equipment of the operating instructions "TAPMOTION® ED" may be
connected to the position transmitter module connections.
► The switchover point of the position transmitter equipment in the motor-
drive unit is not the same as the switchover point of the diverter switch
operation. This depends on the type of diverter switch. This fact should
be noted when project planning the locking circuits between the motor-
drive unit and external equipment (e.g. transformer circuit breaker).
► For external monitoring, locking, and control purposes, it is not there-
fore the position transmitter equipment but the "Tap changer in opera-
tion" position transit contact shown in the connection diagram that
should be used.
11
11.1
Summary of Contents for VACUTAP VR
Page 1: ...On Load Tap Changer VACUTAP VR Installation and Commissioning Instructions 4349315 00 EN ...
Page 246: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 246 4349315 00 EN VACUTAP VR ...
Page 248: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 248 4349315 00 EN VACUTAP VR ...
Page 266: ......
Page 267: ......