Average Weight of Materials
MATERIAL
KG/CU. METER
KG/CU. FOOT
1 CU. YARD
Ashes - Piled Dry
560.70
35
945
Brick Bats
881.10
55
1485
Cement - Portland
1505.88
94
2538
Charcoal
400.50
25
695
Cinders
881.10
55
1485
Clinker - Portland Cement
1361.70
85
2295
Clay - Dry, in Lumps
1009.26
63
1701
Clay - Compact, Natural Bed
1746.18
109
2943
Coal - Anthracite
897.12
56
1512
Coal - Bituminous R of M Piled
881.10
55
1485
Coal - Bituminous Slack, Piled
801.00
50
1350
Coke - Blast Furnace Size
432.54
27
729
Coke - Foundry Size
448.56
28
756
Concrete - Ready to Pour
2370.96
148
3996
Dolomite - Crushed Fine
1521.90
95
2565
Dolomite - Broken Lump
1521.90
95
2565
Earth - Loamy, Dry Loose
1201.50
75
2025
Earth - Dry, Packed
1521.90
95
2565
Earth - Wet (Mud)
1762.20
110
2970
Flue Dust - Blast Furnace
1842.30
115
3105
Flue Dust - Blast Furnace, Wet
2403.00
150
4050
Gypsum - Crushed to 3"
1521.90
95
2565
Gypsum - Calcined
961.20
60
1620
Gravel - Dry, Loose
1762.20
110
2970
Gravel - Dry, Packed
1810.26
113
3051
Gravel - Wet, Packed
1922.40
120
3240
Iron Ore - 60% Iron
4806.00
300
8100
Iron Ore - 50% Iron
4005.00
250
6750
Iron Ore - 40% Iron
3204.00
200
5400
Iron Punchings - Scrap
4325.40
270
7290
Iron Turnings - Scrap
2803.50
175
4725
Limestone - Run of Crushed
1521.90
95
2565
Limestone - Fines Out
1602.00
100
2700
Summary of Contents for 80-160
Page 1: ...OPERATORS MANUAL LOAD KING 80 160 REV B DECEMBER 2020...
Page 2: ...Page Intentionally Blank...
Page 18: ...Page Intentionally Blank...
Page 26: ...26 80 160 Safety 80 160 Safety Sign Locations Right Hand Side View Left Hand Side View...
Page 27: ...27 Rear View Front View...
Page 28: ...28 80 160 Safety Upper Cab...
Page 70: ...70 80 160 Safety Access Egress Rear...
Page 98: ...98 80 160 Assembly...
Page 118: ...118 80 160 Description Of Machine and Controls Lifting controls screen Cab controls screen...
Page 124: ...124 80 160 Description Of Machine and Controls 1 1 PTO Engage Switch...
Page 137: ...137 REPAIRS ADJUSTMENTS REMARKS ITEM REQUIREMENT DATE...
Page 155: ...155 OBSERVE CAUTION NOTES ON OUTRIGGER MOVEMENT WHENEVER SETTING UP OR STOWING OUTRIGGERS...
Page 206: ...Page Intentionally Blank...
Page 209: ...209 8 Install the pin 5 in the guide sheave kickstand 5 9 Remove the lower left hand pin 7 7...
Page 257: ...257 Master Lubrication Chart 13 14 5 4 3 2 2 8 12 9 7 6 15 10 11 BOOM BLOCK TOP VIEW...
Page 300: ...Page Intentionally Blank...
Page 326: ...Page Intentionally Blank...
Page 331: ...331 Repairs Adjustments Remarks Log ITEM REQUIREMENT DATE...
Page 333: ...333...
Page 354: ...Page Intentionally Blank...
Page 362: ...362 80 160 Appendix...
Page 366: ...80 160 Notes...
Page 369: ...80 160 Operator Manual...