5.1 How to start the device
5.1.1 Start-up checklist
Do a check of the device's condition before you energize the device:
•
Are all the wetted components (PEEK element, matching element and gaskets) resistant to
the product in the tank?
•
Does the information on the device nameplate agree with the operating data?
•
If the device is supplied with a magnetic (bypass) level indicator:
If the device is supplied with a magnetic (bypass) level indicator:
If the device is supplied with a magnetic (bypass) level indicator:
If the device is supplied with a magnetic (bypass) level indicator: Did you correctly install the
magnetic level indicator adjacent to the tank?
•
If the device is supplied with a magnetic (bypass) level indicator:
If the device is supplied with a magnetic (bypass) level indicator:
If the device is supplied with a magnetic (bypass) level indicator:
If the device is supplied with a magnetic (bypass) level indicator: Did you remove the float lock
pin from the side process connection at the bottom of the bypass chamber?
•
Do the electrical connections agree with the national electrical codes? Use the applicable
electrical cables with the cable glands.
5.1.2 How to start the device
•
Connect the converter to the power supply.
•
Energize the converter.
5.2 Operating concept
You can read measurements and configure the device with:
•
A connection to a system or PC with PACTware
™
. You can download the Device Type
Manager (DTM) file from the website. It is also supplied on the DVD-ROM delivered with the
device.
•
A connection to a system or PC with AMS
™
. You can download the Device Description (DD)
file from the website. It is also supplied on the DVD-ROM delivered with the device.
•
A connection to a HART
®
Field Communicator. You can download the Device Description (DD)
file from the website. It is also supplied on the DVD-ROM delivered with the device.
For more data about how to use the DTM in PACTware, refer to
Operation on page 41. For more
data about the menu tree for the Basic-DD, AMS and PDM, refer to
Description of HART interface
on page 78.
DANGER!
Before you energize the device, make sure that the supply voltage is correct.
DANGER!
Safe operation in hazardous locations
Safe operation in hazardous locations
Safe operation in hazardous locations
Safe operation in hazardous locations
Make sure that the installation and the wiring of the device agree with the related Ex standards
and regulations. Make sure that the device has the applicable Ex approval for the hazardous
location. For more data, refer to the related Ex certificate of conformity and the supplementary
instructions.
INFORMATION!
The manufacturer sets the parameters for your application in the factory. The 0% level (empty) is
aligned with the center of the bottom process connection and the 100% level (full) is aligned with
the center of the top process connection. You can use the HART communication protocol to
change these parameters.