Chapter 6 Operation
6 - 3
6.4 Power up the inverter
(1) Power up the inverter after confirming the items shown in above section 6.2.
(2) Confirm the LED is emitting like shown below.
- Standard panel : Confirm that both PWR lamp and Key valid lamp are emitting
- Dedicated operator (NES1-OP) : Confirm that the 7-SEG LED is emitting. Display will be the one
set by b038 (Initial display selection). “0.00(output frequency monitor)” will be displayed under
default condition.
(3) Refer to section “6.5” and set required parameters. And then refer to section “6.6 Motor operation”.
Note 1) It will take around 1.5 seconds for the inverter to be ready(each LED emits). Please take into account this delay in case of
an application , which this delay will be important.
Standard panel
NES1-OP
PWR lamp
Key valid lamp
7-SEG LED
Run command
LED
(This LED lights up
when the key operation is enabled.)
Summary of Contents for NES1-002LB
Page 9: ......
Page 21: ......
Page 25: ......
Page 28: ...Chapter 3 Exterior Views 3 3 ...
Page 30: ......
Page 35: ......
Page 53: ......
Page 75: ......
Page 154: ......
Page 196: ......
Page 203: ...Chapter 10 Troubleshooting This chapter describes the troubleshooting methods ...
Page 204: ......
Page 211: ......
Page 219: ......
Page 229: ......
Page 289: ...Appendix Appendix A Appendix A 1 ...
Page 290: ......
Page 292: ...Appendix Appendix 2 ...