C122-E001-10EN
3-23
3.3 Windows Installation
3.3
Windows Installation
To implement a highly reliable system environment with the PRIMEQUEST
machine, Fujitsu recommends the "SAN boot environment," which uses SAN storage
units (e.g., ETERNUS). The workflow for setting up the SAN boot environment is as
follows:
Figure 3.13 Workflow for operation start
Design the SAN boot environment.
- Create diagrams of the Fibre Channel connections and zone settings between the PRIMEQUEST machine and SAN storage.
- Make RAID (LUN_R) settings, and design the SAN storage partition (LUN_V) used to store the SAN boot OS.
Make SAN boot settings for the PRIMEQUEST machine.
- Set up the Fibre Channel card.
- Record the WWPN of each Fibre Channel port.
Set up SAN storage and Fibre Channel switches.
- Install and connect the SAN storage units and the switches according to the Fibre Channel connection diagram created in
"Design the SAN boot environment."
- Retrieve and specify the RAID, partition, and zone information created in "Design the SAN boot environment" and the
WWPNs recorded in "Make SAN boot settings for the PRIMEQUEST machine."
Install the High-Reliability Tools and support drivers.
Install and set up the High-Reliability Tools and drivers. For details on these operations,
see Section 3.3.6, "High-Reliability Tools."
Install Windows.
See Section 3.3.2, "Windows installation using SystemcastWizard Lite,"
Section 3.3.3, "Windows installation using the installation support tool,"
Section 3.3.4, "Windows Installation using the KVM (PRIMEQUEST 580A/540A/580/540/480/440)," or
Section 3.3.5, "Windows Installation using the independent KVM switch (PRIMEQUEST 520/420)."
Preparing for installation
See Section 3.3.1, "Preparing for installation."
Make pre-operation preparations.
Make the necessary preparations before starting partition
operation. For details on this work, see Chapter 4,
"Work Required After Operating System Installation."
Start operation.
Summary of Contents for PRIMEQUEST 400 Series
Page 1: ...C122 E001 10EN Front Cover INSTALLATION MANUAL ...
Page 2: ......
Page 18: ...x C122 E001 10EN NOTE ON SAFETY Extended Power Cabinet ...
Page 19: ...C122 E001 10EN xi NOTE ON SAFETY Extended I O Cabinet ...
Page 20: ...xii C122 E001 10EN NOTE ON SAFETY PCI_Box ...
Page 21: ...C122 E001 10EN xiii NOTE ON SAFETY PRIMEQUEST 520A 520 420 Main unit ...
Page 22: ......
Page 24: ......
Page 42: ......
Page 46: ......
Page 122: ......
Page 186: ......
Page 354: ......
Page 356: ......
Page 394: ......
Page 428: ......
Page 445: ......
Page 446: ...Back Cover ...