Loading and unloading the implement upon delivery
36
Cataya Special BAH0109-1 02.21
Only load the pack top seed drill when it is
mounted on the soil tillage implement and the
roller.
For loading with a crane, select the length of the
sling so that there is no chance of the sling mak-
ing contact, in particular with the seed hopper or
the cover of the seed hopper.
Fig. 4
Required rope lengths:
Rope at the front (Fig. 4/1): 3000 mm
Rope at the rear (Fig. 4/2):
2500 mm
Fasten the
2 slings on the marked fastening points
(Fig. 5/1) on the pack top seed drill.
1 sling on the upper coupling point (Fig. 5/2)
of the soil tillage implement.
Secure the combination properly on the transport
vehicle.
Fig. 5