50 Start-up
Starting up ACS850 drives
1. Power up the drive.
2. Enable the communication between the adapter module and
the drive with parameter
50.01 FBA enable
.
3. With parameter
50.02 Comm loss func
, select how the drive
reacts to a fieldbus communication break.
Note:
This function monitors both communication between the
fieldbus master and the adapter module and communication
between the adapter module and the drive.
4. With parameter
50.03 Comm loss t out
, define the time
between communication break detection and the selected
action.
5. Select application-specific values for parameters
50.04
…
50.11
. Examples of appropriate values are shown in
the tables below.
6. Set the FEPL configuration parameters in group
51
.
•
Select the communication profile with parameter
51.02
.
•
Configure the network settings with parameters
51.03
and
51.04
.
7. Validate the settings made in parameter group
51
with
parameter
51.27 FBA par refresh
.
8. Set the relevant drive control parameters to control the drive
according to the application. Examples of appropriate values
are shown in the tables below.
Summary of Contents for FEPL-02 Ethernet POWERLINK
Page 4: ......
Page 10: ...10 Table of contents ...
Page 20: ...20 About the manual ...
Page 28: ...28 Mechanical installation ...
Page 63: ...Start up 63 2 To add the adapter module right click the IF3 list entry and then click Insert ...
Page 69: ...Start up 69 3 In the Project transfer dialog box click OK 4 Wait for the transfer to finish ...
Page 70: ...70 Start up When the transfer is finished the PLC starts up in the RUN mode ...
Page 90: ...90 Communication profiles ...
Page 100: ...100 Communication protocol ...
Page 104: ...104 Diagnostics ...
Page 108: ...108 Technical data ...