Option 109
Below is an example (available when SBN=0001):
1. Confirm that the upper side phase order of MCB and MB1 are clockwise (customer’s
responsibility);
2. Disconnect the motor cable at the motor side;
3. Short-circuit both the input cable and output 3 phases cables of the VFD one by one;
4. Close MSS1 (in test position);
5. Check the underside phase order of MCB and MB1 with multimeter at measuring
points one by one. Make sure the phase order of this circuit is correct.
6. Check other main circuits phase order as the same procedure one by one (if
SBM>=0002)
Phase order check for PTs
1. Check the primary cable connection of PTs and make sure the phase order is correct.
2. Check the wirings connection between the secondary side of PTs and Rsyc-01 board.
Make sure the phase order is correct.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...