Option 133
3. General configuration of speed follower
20.6
Ext2 commands
M/F link
20.7
Ext2 start trigger type
level
26.12
Torque ref2 source
M/F reference 2
60.1
M/F comm port
RDCO CH2
Channel of DDCS M/F
60.2
M/F node address
2 to 60
ID of this Follower
60.3
M/F mode
DDCS follower
60.9
M/F comm loss
function
Fault
Follower’s action when comm loss happens
60.11
M/F ref2 type
Torque
62.1
M/F data 1 selection
CW 16bit
Follower selects the data which receive from
the master. The data value shown as
P62.25~27
62.2
M/F data 2 selection
Ref1 16bit
62.3
M/F data 3 selection
Ref2 16bit
61.1
M/F data 1 selection
SW 16bit
(Optional) Follower select the data which
transmit to the master, and they are effective
when this follower is selected by Master’s
P60.14
61.2
M/F data 2 selection
User dependent
61.3
M/F data 3 selection
User dependent
ACS580MV Follower Parameter Settings
—
Speed Follower
Parameter
Name
Setting
Description
19.11
Ext1/Ext2 selection
Ext2
19.14
Ext2 control mode
Speed
20.6
Ext2 commands
M/F link
20.7
Ext2 start trigger type
level
22.12
Speed ref2 source
M/F reference 1
60.1
M/F comm port
RDCO CH2
Channel of DDCS M/F
60.2
M/F node address
2 to 60
ID of this Follower
60.3
M/F mode
DDCS follower
60.9
M/F comm loss function
Fault
Follower’s action when comm loss
happens
60.10
M/F ref1 type
Speed
62.1
M/F data 1 selection
CW 16bit
Follower select the data which receive
from the master. The data value
shown as P62.25~27
62.2
M/F data 2 selection
Ref1 16bit
62.3
M/F data 3 selection
Ref2 16bit
ACS580MV Follower Parameter Settings — Torque Follower
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...