Standard Commissioning Process 75
1. Check all the control cables have been assembled according the customer interface
drawing.
2. Select the type of connection to overriding system in DriveStartup: Standard IOs,
External module IOs or Fieldbus.
3. Check the configuration in below parameter settings:
•
Group 19 Operation mode
•
Group 20 Start/stop/direction
•
Group 22 Speed reference selection
•
Group 82 Charging/MCB control
•
Group 10 Standard DI, RO
•
Group 12 Standard AI
•
Group 13 Standard AO
•
Group 14/15/16 I/O extension module 1/2/3
•
Group 51 FBA A settings
•
Group 52 FBA A data in
•
Group 53 FBA A data out
•
Group 82 Charging, MCB control
4. Set the parameters as required and check the signals are correct sent and received
between the drive and overriding system.
Hot commissioning by DriveStartup
After completing the tasks in the previous chapters, the converter can be energized.
Close MCB and Load Power Module software
After MCB has been closed and medium voltage introduced to the converter, power
modules (PMs) boot up.
BCON controller checks the SW version to each PM.
If all PMs don`t have the same version or if the PM SW version is outdated BCON will
initiate SW downloading to PMs.
Due to safety reasons, during SW update MCB will be open (fault 607E “PM software
update in process” is active).
The fault cannot be reset until the SW update is finished (this is indicated by another fault
message: 607F “PM SW update done”).
Please operate the converter according to the description of “DriveStartup”.
Cooling and heating system testing
•
Check the configuration and feedback signals of the cooling fans. Group 87 Cooling
system, parameter 17.5/87.40 INU/TRU fan feedback.
DANGER
From this step MCB is in normal position and controlled only by
ACS580MV. Medium voltage can be connected to the converter! Confirm
safety area of motor is cleared and auxiliary equipment of motor is in operation.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...