Standard Commissioning Process 73
•
Press emergency off button on front door, fault
AFEB Emergency OFF button pressed
is active. Release emergency off button, the fault should deactivated.
•
Press ON button on front door, MCB should be closed. Press OFF button on front
door, MCB should be opened.
•
Press ON button on front door, MCB should be closed. Press emergency off button on
front door, MCB should be opened and fault
AFEB Emergency OFF button pressed
is
active. Release emergency off button, the fault should deactivated.
•
Press ON button on front door, MCB should be closed. Wait more than 3 seconds,
Fault E110 DC link charging timeout should activate, MCB trips.
•
Zoom out the graph. Verify that the MCB control and feedback signals respond in the
correct sequence.
•
Save measurement in the project. Then attach plot to report.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...