54 Standard Commissioning Process
•
Please operate the converter according to the description of “DriveStartup”.
Loading the DSP software manually to power modules
•
Necessary tools: 5.5 VDC power, USB to POF cable and fiber cable.
•
Install the Tera term programing tool, select the default components.
•
Check and confirm the drive has been discharged and door lock is released.
•
Open the INU door and then switch off the control power supply.
•
Connect the POF link to power module and USB to PC.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...