Standard Commissioning Process 65
•
Fill in all necessary information.
Note:
Must fill in the full type code in Drive configuration, such as:
ACS580MV-066-A04A-J5-
010+CCS00
00+CIT000
0+TRR0073
+EWT0000
+CPF0002
+WMT0001
The full type code can be copied from the project information in MoR by search the series
number. If necessary contact MV Drives Supportline.