50 Standard Commissioning Process
Loading the CVMI2 firmware
•
Install the XILINX lab tools 14.7. Refer to the previous step.
•
Switch off the control power.
•
Connect XILINX platform cable USB II to X1301 connector on CVMI2.
•
Switch on the control power.
•
Run PROG_LXES.bat batch file to program the CVMI2. (folder: \06_CVMI2 FW)
Note:
If the error information like below, it means that the location of the IMPACT program
needs to be added to the system path.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...