Option 115
3. Marshalling PLC parameter setting
The following parameters are necessary.
Marshalling PLC
parameter
Setting Description
Par.1 Control
source
IOs control
(example)
Select Marshalling PLC control source.
Par.2 Number of
motors
2 (example)
Define number of motors.
Par.3 MB
feedback signal
TWO
(example)
Define how many feedback signals MB has.
Par.4 MSS
feedback signal
TWO
(example)
Define how many feedback signals MSS has.
Par.5 MB
command signal
Pulse
(example)
Define control signals type of MB.
Par.6 MSS
command signal
Pulse
(example)
Define control signals type of MSS.
Par.7 MB pulse
time
3s
(example)
Define pulse time of MB control signal.
Par.8 MSS pulse
time
3s
(example)
Define pulse time of MSS control signal
Par.9 MB close
time limit
3s
(example)
Define maximum operating time for closing MB
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...