100 Option
Insulation test
The insulation test is not recommended, if necessary check the description in
Commissioning for MBU=0001 option
•
Confirm the MCB has been racked out and grounded.
•
Ground the input busbar in TRU cabinet by grounding harness for safety.
•
Connect the control cables among the MCB, MBU and COU cabinet.
•
Disable the local close push button on MCB cabinet.
•
Connect the auxiliary control power supply to the cabinet.
Check of the isolation switches position
•
Follow the operation sequence, operate the switches of QS1(Q1), QS2(Q2) and
QS3(Q3).
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...