Appendix E - Startup and Commissioning Checklist
_______________________________________________________________________________________________________________
MNL000542
Revision 1
03/26/2018
BSGS eV / BULKGUARD eV
© Versum Materials, Inc. as of the revision and date shown. All rights reserved.
Confidential and Proprietary Data
Page APP
E
-
4
3. Safety Protocols / Equipment Checks
Initials
or N/A
Date
A.
Hazardous gas monitors / leak detection for process gas installed, wired, and tested by Customer or
Customer’s installation contractor (if applicable).
B.
Verify exhaust duct / scrubber exhaust lines (if applicable) are complete, flowing, and balanced.
Confirm balancing damper on cabinet is closed if using exhaust ducts. Record Exhaust Duct Field
Piping installation drawing number and revision.
Dwg #
_______________
, Rev.
___
. Verify exhaust flow tell tails are installed.
C.
Customer Life Safety System (LSS) I/O for BSGeV installed, wired, labeled, and point-to-point tested
by Customer or installer.
D.
Customer safety protocols and checks / signoffs complete and all power is ready and authorized to
energize. Equipment has tags / nameplates showing where source of electrical power originates.
E.
Conduit seals installed, packed, and poured once electrical checkout complete and all wiring verified.
Paint conduit seal red once poured.
F.
Danger / warning stickers installed on each piece of equipment as required by Customer and VERSUM
MATERIALS, INC. safety protocols.
G.
Voltage level warning stickers installed on each piece of equipment as required by Customer and
VERSUM MATERIALS, INC. safety protocols.
H.
Complete the VERSUM MATERIALS, INC. Operational Readiness Inspection (ORI) and verify the
ORI is signed off by Customer representatives.
I.
Verify Customer Safety Level 2 (SL2) approval for Hazardous Gas is complete.
4. Electrical Commissioning and Checkout
Initials
or N/A
Date
A.
Obtain copy of BSGeV Elementary Wiring Diagram used to manufacture this BSGeV. Record drawing
number and revision. Dwg # _
_____________
, Rev.
___
.
B.
Verify Third Party Certification from a Nationally Recognized Testing Laboratory (NRTL) is
complete. Record NRTL listing number for each BSGeV module:
_________________
.
C.
Verify all equipment is properly installed in a General Purpose area or properly equipped and rated for
installation within a Hazardous / Classified area.
D.
If any BSGeV equipment is installed within an electrically rated Hazardous / Classified area, list the
Hazardous Classification of the area: Class:
___
, Division:
___
, Group:
___
. List each piece of
BSGeV equipment that is installed within this Hazardous Area:
__________________
_________________________________________________________________________
. Verify
that each piece of electrical equipment (devices, conduit, fittings, reducers, etc.) is properly rated (or
properly equipped) for installation within this Hazardous Area.
E.
Verify all field conduit and wiring installed per design package. Record drawing number and revision
of electrical installation drawing. Dwg # _
___________________
, Rev.
___
.