Chapter 2 - Installation
_______________________________________________________________________________________________________________
MNL000530
Revision 1
03/15/2018
BSGS eV / BULKGUARD eV
© Versum Materials, Inc. as of the revision and date shown. All rights reserved.
Confidential and Proprietary Data
Page
2
-
45
Installation and Pre-Facilitation Checklist
A GASGUARD
®
BSGS eV / BULKGUARD
®
eV Installation and Pre-Facilitation Checklist is
provided in an appendix of this manual. This checklist will assist the owner/installer with items to be
completed prior to startup. The Installation and Pre-Facilitation Checklist is included in Appendix D
of this manual.
Startup and Commissioning Checklist
A GASGUARD
®
BSGS eV / BULKGUARD
®
eV Startup and Commissioning Checklist is provided in
an appendix of this manual. This checklist is used to verify that the system is connected properly and
is ready for the Operational Readiness Inspection, commissioning, and start up
.
The Startup and
Commissioning Checklist is included in Appendix E of this manual.
Operational Readiness Inspection
Before a BSGS eV / BULKGUARD eV module or system can be started up, an Operational Readiness
Inspection (ORI) must be completed. The ORI is a checklist that assures equipment placement,
connection to all required utilities, verification of operability, startup and eventual commissioning prior
to the introduction of process gas into the module or system. The ORI checklist is included in
Appendix F of this manual.
OSHA Process Safety Management (PSM)
The United States Government, through OSHA, has established threshold quantities of hazardous
gases. When exceeded, OSHA requires the system owner to establish a PSM program to inform
employees of the operational characteristics and hazards of system operation. Contact OSHA, or ask
your Versum Materials, Inc. representative for information on PSM threshold quantities and if
establishing a PSM program applies to your facility.