![Hitachi RAS-(2-6)HVNP1(E) Скачать руководство пользователя страница 76](http://html.mh-extra.com/html/hitachi/ras-2-6-hvnp1-e/ras-2-6-hvnp1-e_service-manual_2139503076.webp)
3 Piping work and
refrigerant charge
62
SMGB0087 rev.0 - 12/2013
3.1 General notes before performing pipe work
3.1.1 Piping Materials
1
In order to avoid supply problems in terms of local regulations and quality, prepare locally-supplied copper pipes.
N O T E
In case of using copper pipes for piping sections bigger than Ø19.05 mm (3/4 inches), flaring work cannot be performed.
If necessary, use a joint adapter.
2
Select the piping size with the correct thickness and correct material able to withstand sufficient pressure.
3
Select clean copper pipes. Make sure there is no dust and moisture inside. Blow the inside of the pipes through with
oxygen-free nitrogen to remove any dust and foreign materials before connecting pipes.
4
After connecting the refrigerant piping, seal the open space between the knockout hole and refrigerant pipes by using
insulation material as shown below:
A. Insulator material.
B. Field-supplied refrigeration pipe.
C A U T I O N
• Do not use saws, grindstones or other tools which cause copper
powder.
• When cutting pipes, secure the part for brazing in accordance
with both national and local regulations.
• Use security glasses and gloves for cutting or welding works.
Piping Connection
When connecting liquid piping for units with piping longer than 15 meters, apply a piping size of Ø9.52 mm (3/8 inches). Fix
the connecting pipe as shown in the following figure using the insulation attached to the Indoor Unit.
A. Use the flare nut of the indoor unit.
B. Insulate this part with the attached insulation.
C. Fix this part with the attached cord band or with tape.
D. Field-supplied refrigerant piping.
E. Field-supplied insulation.
F. Brazing.
G. Make flares after attaching flare nut to the connecting pipe in the
Multi-kit package.
H. Insulation attached to indoor unit.
I. Indoor unit.
N O T E
• A system with no moisture or oil contamination will give maximum performance and lifecycle compared to a poorly
prepared system. Take particular care to ensure that all copper piping is clean and dry internally.
• To ensure this, blow oxygen-free nitrogen through the pipes.
Содержание RAS-(2-6)HVNP1(E)
Страница 2: ......
Страница 4: ... II ...
Страница 28: ......
Страница 134: ...4 Electrical wiring 120 SMGB0087 rev 0 12 2013 4 7 3 RAS 3HVNP1E 1 230V 50Hz XEK01261_0 ...
Страница 136: ...4 Electrical wiring 122 SMGB0087 rev 0 12 2013 4 7 4 RAS 4 6 HVNP1E 1 230V 50Hz XEK01262_1 ...
Страница 138: ...4 Electrical wiring 124 SMGB0087 rev 0 12 2013 4 7 6 RAS 4 6 HNP1E 3N 400V 50Hz XEK01263_2 ...
Страница 140: ...4 Electrical wiring 126 SMGB0087 rev 0 12 2013 4 7 7 RAS 4 6 HVNC1E 1 230V 50Hz XEK01264_4 ...
Страница 142: ...4 Electrical wiring 128 SMGB0087 rev 0 12 2013 4 7 8 RAS 4 6 HNC1E 3N 400V 50Hz XEK01265_4 ...
Страница 144: ...4 Electrical wiring 130 SMGB0087 rev 0 12 2013 4 7 10 RAS 8 10 HN P C E 3N 400V 50Hz XEK01288_3 ...
Страница 146: ...4 Electrical wiring 132 SMGB0087 rev 0 12 2013 4 7 12 RAS 12HN P C 3N 400V 50Hz 7T146440 ...
Страница 148: ......
Страница 204: ......
Страница 220: ......
Страница 332: ......
Страница 353: ...9 Spare parts 339 SMGB0087 rev 0 12 2013 9 RAS 8 10 HNCE Spare Parts Document EPN 201211D ...
Страница 354: ...9 Spare parts 340 SMGB0087 rev 0 12 2013 9 6 2 Electrical parts View from P Spare Parts Document EPN 201211D ...
Страница 362: ......
Страница 484: ......
Страница 496: ......
Страница 497: ......