Chapter 6 Fastening Operation
PAGE 6-29
●
Rate Check
Three torque rate areas capable of judging the rise of torque vs. angle (slope) can be used to monitor the
fastening operation.
A rate start torque (angle) and a rate end torque (angle) set the boundaries of each area and the torque
slope (slope of the torque vs. angle) between the two points is calculated to make the judgment once the
end point is reached
. (Example: 25N•m÷100deg=0.25N•m/deg).
The fastening operation is ended when the measurement value of each rate falls outside the the high and
low limit ranges.
The start torque (angle) and end torque (angle) of the respective rates can be set freely without any relation
to the order of the rates and the set values of the other rates.
[To Customers Using the older FUSION Handheld Nutrunner Systems]
There are parameter D-Nos. that are changed in name and function.
Please reference the corresponding table on the following page for correct
parameter setup
117: Rate 3
End Torque
116: Rate 3
Start Torque
115: Rate 2
End Torque
114: Rate 2
Start Torque
113: Rate 1
End Torque
112: Rate 1
Start Torque
305: Rate 3 High Limit
206: Differ Angle
207: Differential - Angle
209: Rate 1 End Angle
208: Rate 1 Start Angle
304: Rate 3 Low Limit
301: Rate 1 High Limit
302: Rate 2 Low Limit
303: Rate 2 High Limit
300: Rate 1 Low
Limit
211: Rate 2 End Angle
212: Rate 2 Start Angle
213: Rate 3 End Angle
212: Rate 3 Start Angle
Содержание Handheld Nutrunner HFC3000
Страница 2: ...www fec usa com Copyright 2017 FEC AUTOMATION SYSTEMS All Rights Reserved ...
Страница 14: ...Notes ...
Страница 15: ...Chapter 1 Outline PAGE 1 1 Chapter 1 Outline 1 ...
Страница 21: ...Chapter 2 Specifications PAGE 2 1 Chapter 2 Specifications 2 ...
Страница 28: ...Chapter 2 Specifications PAGE 2 8 Blank Page ...
Страница 29: ...Chapter 3 Sysytem Description PAGE 3 1 Chapter 3 System Description 3 ...
Страница 36: ...Chapter 3 System Description PAGE 3 8 Memo ...
Страница 37: ...Chapter 4 Installation and Wiring PAGE 4 1 Chapter 4 Installation Wiring 4 ...
Страница 67: ...Chapter 5 Power Up and Operational Tests PAGE 5 1 Chapter 5 Power Up and Operational Tests 5 ...
Страница 71: ...Chapter 6 Fastening Operation PAGE 6 1 Chapter 6 Fastening Operation 6 ...
Страница 151: ...Chapter 7 Troubleshooting PAGE 7 1 Chapter 7 Troubleshooting 7 ...
Страница 169: ...Chapter 8 Options PAGE 8 1 Chapter 8 Options 8 ...
Страница 181: ...Chapter 9 Fieldbus I O Interfaces PAGE 9 1 Chapter 9 Fieldbus I O Interfaces 9 ...
Страница 207: ...Chapter 9 Fieldbus I O Interfaces PAGE 9 27 9 3 2 Description of the hardware RUN LED ERROR LED CC Link Connector ...
Страница 229: ...Chapter 9 Fieldbus I O Interfaces PAGE 9 49 Blank Page ...
Страница 230: ......
Страница 231: ......