Initial start-up, inspection and maintenance
StepsĂćĂinitial start-up, inspection and maintenance
For further instructions concerning the individual steps see pages indicated.
Commissioning steps
Inspection steps
Maintenance steps
Page
C
1. Filling the heating systemĂ
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C
2. Checking the electrical mains connection
C
3. Changing the language (if necessary)Ă
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C
M
4. Checking the gas typeĂ
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C
5. ChangingĂtheĂgasĂtype
(seeĂseparateĂinstallationĂinstructions)
C I
M
6. Checking the idle and the supply pressureĂ
8
. . . . . . . . . . . . . . . . . . . .
C
7. Function sequence and possible errors during
initial start-upĂ
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C
M
8. Checking the CO
2
settingsĂ
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C
9. Max. outputĂ
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C
M
10. Fully checking the burner
(recordĂvaluesĂon pageĂ108 of commissioning report)
C
11. Leak testing the BF system (circular gap check)Ă
16
. . . . . . . . . .
I
M
12. Removing the burner and checkingĂthe
burner gasket for leaksĂ
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I
M
13. Checking the burner gauze assemblyĂ
18
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I
M
14. CheckingĂ&ĂadjustingĂignitionĂ& ionisationĂelectrodesĂ
18
. . . .
I
M
15. Cleaning the combustion chamber/heating surfaces
and installing the burnerĂ
19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I
M
16. Checking the condensate drainĂ
20
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I
M
17. Checking the neutralising system
(if installed)
Ă
20
. . . . . . . . . . . . . . . . .
C I
M
18. Checking all connections on the primary and on the
secondary side for leaks
C
M
19. Checking the diaphragm expansion vessel and
the system pressure
C I
M
20. Checking the function of all safety valves
C I
M
21. Checking the tightness of electrical connections
5692Ă485
G
B
Summary of Contents for Vitodens 200
Page 25: ...25 Initial start up inspection and maintenance 5692Ă485 GB ...
Page 96: ...96 Control unit for weather compensated mode with Comfortrol prog unit 5692Ă485 GB ...
Page 99: ...101 5692Ă485ĂGB ...
Page 105: ...109 Appendix Maint service Maint service Maint service Maint service 5692Ă485ĂGB ...
Page 107: ...111 Appendix Maint service Maint service Maint service Maint service 5692Ă485ĂGB ...
Page 109: ...113 Appendix Maint service Maint service Maint service Maint service 5692Ă485ĂGB ...