CHAPTER 3:
Installation and Setup
Model CRX-6.5K Probe Station
3.6 Assembling a
Basic Probe
System
Configuration
Use the following procedures to complete the assembly process. If a Lake Shore
assisted installation was purchased with the system, the installer will begin at this
point.
3.6.1 Positioning and
Leveling the CCR Stand
For proper operation of the Model CRX-6.5K, the CCR stand must be centered relative
to the outer probe station stand, and it must be levelled. In operation, the inner CCR
stand and the outer probe station stand are not connected; this minimizes the
vibration from the CCR at the sample stage.
The level and wrenches used to uncrate the probe station are required for this procedure.
Use this procedure to position and level the CCR stand:
1. Locate the three flexible red vibration isolation pads in the Model CRX-6.5K
accessories box. Place them under the three feet of the CCR stand. Make sure the
red pad for each foot is centered under the foot.
2. Locate the ¾ in or adjustable wrench provided in the Model CRX-6.5K tool kit.
Use it to lower the CCR stand feet until they just touch the red pads. Do not add
tension to the feet at this step.
3. Using a
q
in or adjustable wrench, remove the four bolts that lock the CCR stand
to the probe station stand.
4. Using the ¾ in wrench, continue to lower the CCR stand feet until the weight of
the CCR stand is removed from the four red spacing washers located between the
CCR stand and outer probe station stand.
5. Remove the four red spacing washers and associated hardware; store this
hardware with the other shipping provisions removed from the probe station in
section 3.3.5
6. Locate the spacing fixture (DC5058) in the Model CRX-6.5K tool kit. This is a
rectangular aluminum block approximately 58 mm (2.3 in) long and 13 mm
(0.51 in) wide.
7. Place the spacing fixture as shown in FIGURE 3-11 between the top vacuum
chamber and the CCR vacuum shroud. This will be used to set the proper 58 mm
(2.3 in) spacing between the bottom of the vacuum chamber and the top of the
vacuum shroud.
8. Place the level on the CCR stand.
FIGURE 3-10
Left: Vibration isolation pads positioned under the CCR stand feet; Right: Remove the locking bolts and red spacing washers