Lower each of the four probe station outer stand feet until the bottom of the
probe station stand is approximately 73 mm (2.875 in) from the floor. This
will take the weight of the probe station off of the long red cross braces. For
uneven flooring, it is acceptable if the bottom of the feet are lowered up to 85
mm below the bottom of the stand (FIGURE 3-6).
Do not lower the probe station stand feet so that the bottom of the probe station
stand is more than 85 mm above the floor. Doing so will disengage the feet from
the stand causing the station to tip and possible injury or death.
c.
Using a
q
in or adjustable wrench, remove the bolts that secure the long red
cross braces from the probe station (FIGURE 3-7).
d.
Move the long red cross braces out of the work area. Save these in the event
that you need to return the probe station.