The following figure shows the logic scheme for the breaker failure element:
Figure 5–20: LOGIC SCHEME FOR 50BF
The breaker failure element has three levels. The first one is called “Retrip” or “Supervision”. This operation level can be
used to give a signal to the breaker on which the initial opening has been executed. This is sometimes a usual practice; 50
milliseconds after the trip signal, a retrip signal is sent to the breaker.
Besides the supervision or retrip level, there are two additional levels, known as “Hiset” and “Lowset”. These two levels,
together with their time delays, allow executing complex protection schemes. Additionally to these two supervision levels,
there is a second time stage called “second step”.
Operation of breaker failure elements by level (supervision, hi set and lo set) is produced when the current level is higher
than the set current for the pickup of each level during the time set in the corresponding delay setting.
High and low levels constitute a second step level; for the pickup of this second level, only the pickup of any of the two
levels (hiset and loset) is required. For the element pickup to dropout it is required that the current is under the pickup levels
of both hiset and loset settings. Once the second level time delay has expired, a “Second Step” trip signal will be issued.
50BF element incorporates also a no current tripping element, and an internal arc element. The no-current trip element is
governed only by the status of the breaker auxiliary contact; once the external breaker failure initiation signal is received, if
the breaker status does not change to open during the set time in the element (No Current Delay), the corresponding
breaker failure signal is issued (BKR FAIL NO CURRENT),
The internal arc element inside the breaker failure element is independent from the external breaker failure signal; this
element is used to detect arcing produced with an open breaker; if a higher current that the set level is detected during a
period that is longer than the set delay for the element (Internal Arc Delay), and the breaker is open, the corresponding
internal arc signal will be issued (INTERNAL ARC).
Summary of Contents for Multilin W650
Page 2: ......
Page 10: ...VIII W650 Wind Generator Protection System GEK 113032A TABLE OF CONTENTS ...
Page 30: ...1 20 W650 Wind Generator Protection System GEK 113032A 1 4 W650 HARDWARE 1 GETTING STARTED 1 ...
Page 140: ...4 72 W650 Wind Generator Protection System GEK 113032A 4 3 WEB SERVER 4 HUMAN INTERFACES 4 ...
Page 406: ...11 22 W650 Wind Generator Protection System GEK 113032A 11 15 RECLOSER 79 11 COMMISSIONING 11 ...
Page 446: ...A 22 W650 Wind Generator Protection System GEK 113032A A 1 LOGIC OPERANDS APPENDIXA A ...
Page 622: ...F 2 W650 Wind Generator Protection System GEK 113032A F 1 GE MULTILIN WARRANTY APPENDIXF F ...