f.
Verify Isolation
3.
Temporary removal of LOTO and re-energization of a machine or equipment may be
performed when power is needed for testing or positioning. When testing you must:
a.
Ensure the machine is operationally intact.
b.
Notify all Authorized or Affected Employees who are working on the equipment or are in
the area that the equipment is going to be tested and to move to a safe area.
c.
Verify controls are in the "off" position.
d.
Remove LOTO Locks and tags.
e.
Energize and proceed with testing.
f.
After testing, de-energize, verify system isolation, and re-apply LOTO Locks and Tags.
4.
When removing Lockout/Tagout the following steps must be followed:
a.
Communicate to all Affected Employees.
b.
Verify the safety of the area.
c.
Ensure the safety devices and guards are in place.
d.
Return system functions.
e.
Remove your lock and tag.
f.
Communicate system re-energization.
g.
Re-energize and test equipment.
1.2.4
Certified Electrical Contractor Statement
All electrical Installations that are preliminary to positioning of the equipment at the site prepared
for the equipment shall be performed by licensed electrical contractors. In addition, electrical feeds
into the Power Distribution Unit shall be performed by licensed electrical contractors. Other
connections between pieces of electrical equipment, calibrations and testing shall be performed by
qualified GE Medical personnel. The products involved (and the accompanying electrical
installations) are highly sophisticated, and special engineering competence is required. In
performing all electrical work on these products, GE will use its own specially trained field
engineers. All of GE’s electrical work on these products will comply with the requirements of the
applicable electrical codes. The purchaser of GE equipment shall only utilize qualified personnel
(i.e., GE’s field engineers, personnel of third-party service companies with equivalent training, or
licensed electricians) to perform electrical servicing on the equipment.
1.2.5
Important... X-Ray Protection
CAUTION
X-ray equipment if not properly used may cause injury. Accordingly, the instructions herein should
be thoroughly read and understood by everyone who will use the equipment before you attempt to
place this equipment in operation. The General Electric Company, Medical Systems Group, will be
glad to assist and cooperate in placing this equipment in use.
Although this apparatus incorporates a high degree of protection against x-radiation other than the
useful beam, no practical design of equipment can provide complete protection. Nor can any
practical design compel the operator to take adequate precautions to prevent the possibility of any
persons carelessly exposing themselves or others to radiation.
It is important that anyone having anything to do with x-radiation be properly trained and fully
acquainted with the recommendations of the National Council on Radiation Protection and
Measurements as published in NCRP Reports available from NCRP Publications, 7910 Woodmont
Summary of Contents for Healthcare eXplore Locus SP
Page 2: ...This page is intentionally left blank...
Page 12: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page 12...
Page 13: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page13...
Page 37: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page37...
Page 228: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page 228...