4. Commissioning
4−8
Festo P.BE−MPA−EN en 0502b
4.3
Checking the valves and the valve−actuator combination
Please note
Before commissioning the MPA valve terminal, note the
specifications concerning the medium, see section "In
stallation," section "Pilot control of the valve solenoid coils
(auxiliary pilot air)."
The MPA valve terminal should be commissioned as follows:
Commissioning variants
Activity
Preliminary test of the pneuma
tic tubing
Testing the valve−actuator com
bination by means of the manual
override
Complete commissioning of the
complete system
Installing and connecting the
complete system
Program control via PLC/indu
strial PC
Table4/3:
Commissioning variants
How to commission the pneumatic components by means of
the manual override is described below.
Commissioning of the CPX terminal is described in the ap
propriate manual for the CPX field bus node.
Summary of Contents for MPA-FB Series
Page 2: ......
Page 4: ...Contents and general instructions II Festo P BE MPA EN en 0502b...
Page 8: ...Contents and general instructions VI Festo P BE MPA EN en 0502b...
Page 17: ...Summary of components 1 1 Festo P BE MPA EN en 0502b Chapter 1...
Page 30: ...1 Summary of components 1 14 Festo P BE MPA EN en 0502b...
Page 31: ...Fitting 2 1 Festo P BE MPA EN en 0502b Chapter 2...
Page 47: ...Installation 3 1 Festo P BE MPA EN en 0502b Chapter 3...
Page 55: ...3 Installation 3 9 Festo P BE MPA EN en 0502b 1 2 3 Fig 3 2 Disconnecting the tubing...
Page 79: ...Commissioning 4 1 Festo P BE MPA EN en 0502b Chapter 4...
Page 96: ...4 Commissioning 4 18 Festo P BE MPA EN en 0502b...
Page 97: ...Diagnosis and error treatment 5 1 Festo P BE MPA EN en 0502b Chapter 5...
Page 139: ...Technical appendix A 1 Festo P BE MPA EN en 0502b Appendix A...
Page 151: ...Accessories B 1 Festo P BE MPA EN en 0502b Appendix B...
Page 161: ...Index C 1 Festo P BE MPA EN en 0502b Appendix C...
Page 162: ...C Index C 2 Festo P BE MPA EN en 0502b Contents C Index C 1...