6.
Use the arrow keys to enter the desired value for this digit. Press ENTER to select the
displayed value; the cursor moves to the second digit. Select the value for the
second digit and press ENTER. Continue this process for each digit of the security
code.
When the fourth digit is correctly entered, the processor enters Mode
5
.
7.
When in Mode
5
, select
Calibrate
using the keypad arrow keys; press ENTER to access
the Calibrate menu.
8.
Use the arrow keys to select
SET DETECTORS
; press ENTER.
The display shows the D1 and D2 detector levels.
CAUTION!
If the analyzer is not in
SET UP
mode, the gas cell at the source unit periodically
interrupts the IR beam and make alignment difficult.
9.
Adjust the receiver alignment, using the adjusting nuts,
plane, then in the other.
As a rule, the D2 detector level is affected to a greater extent by adjustment in one
particular plane. The D1 detector level is affected more by adjustment in the other
plane.
10.
Make sure the maximum possible values of both D1 and D2 are reached. After you
achieve alignment, tighten the locking nuts.
Note
The alignment of the receiver unit is important. Make sure to obtain the maximum values of
D1 and D2.
11.
If the displayed detector level is below 5000, increase the gain at the control unit to
between 12000 and 14000.. If the detector level is above 15000, reduce the gain to
between 12000 and 14000.
Refer to
12.
To fine tune the alignment, repeat adjustments of
at the source unit. Again,
make sure the values of D1 and D2 are appropriate. Lock the source unit in place
when the maximum values are achieved.
13.
When you have properly completed the alignment, there is rarely any need for
further alignment adjustments.
3.5
Detector levels
The gain of the detector signals is set in two locations:
1.
In the receiver, two potentiometers set the gain. Refer to
.
Configuration and startup
Reference Manual
29
Summary of Contents for Rosemount CCO 5500
Page 4: ......
Page 8: ...Contents iv Rosemount CCO 5500 ...
Page 28: ...System Wiring Diagram Figure 2 7 Install 20 Rosemount CCO 5500 ...
Page 32: ...Install 24 Rosemount CCO 5500 ...
Page 88: ...Operation 80 Rosemount CCO 5500 ...
Page 98: ...Maintenance 90 Rosemount CCO 5500 ...
Page 108: ...Troubleshooting 100 Rosemount CCO 5500 ...
Page 110: ...Spare parts 102 Rosemount CCO 5500 ...
Page 122: ...Return equipment to the factory 114 Rosemount CCO 5500 ...
Page 123: ...Return equipment to the factory Reference Manual 115 ...