Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
–
(2) mounting brackets
(4) 6-32 flat-head screws
•
Rails and fasteners:
–
(2) sliding rail assemblies (left and right)
–
(2) rear hold-down brackets
–
(12) hex-head screws
–
(4) U-shaped 10-32 clip nuts
•
EBM user’s guide
NOTE
Discard the EBM user’s guide. Use this user’s guide to install the EBM.
33..1155
R
Raacckk S
Seettuupp ffoorr tthhee EEB
BM
M
CAUTION
The EBM is heavy (see page 139 ). Removing the EBM from its carton requires a minimum of two people. Use
the corrugated lifting sling (packaged with the UPS) to move the UPS.
NOTE
Mounting rails are required for each individual cabinet.
To install the EBM rail kit:
1.
Loosen the assembly wing nuts on both rail assemblies and adjust the rail size for the depth of your rack
(See
) .
Figure 31. Adjusting the Rail Depth
Rear
Front
Rail Assembly
Assembly Wing Nuts
2.
Select the proper holes in the rail for positioning the EBMs in the rack.
Place the first rail for the first EBM above the UPS, using positions 37 and 42 for the front hex-head
screws. If you are installing additional rails, place the next rail 4 holes above the last installed screw (see
) .
NOTE
Verify that the hole patterns on the rails and mounting brackets align with the hole
pattern on the rack.
Summary of Contents for BladeUPS none
Page 8: ...viii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Table of Contents ...
Page 12: ...xii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Figures ...
Page 14: ...xiv Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Tables ...
Page 20: ...6 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Introduction ...
Page 134: ...120 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Metering ...
Page 160: ...16420164914 164201649 14 ...