Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
8.
Wait for the UPS front panel display to illuminate.
The
indicator flashes on the UPS.
9.
Check the UPS front panel display for active alarms or notices (other than “Batteries Disconnected”).
Resolve any active alarms before continuing. See .
10. Switch the UPS battery circuit breaker to the ON (|) position.
11. If optional EBMs are installed, switch all EBM battery circuit breakers to the ON (|) position.
12. Verify that the “Batteries Disconnected” alarm has cleared. Verify that no other alarms appear on the UPS
front panel display.
If the
indicator is flashing, do not proceed until all alarms are clear. Check the UPS status from the
front panel to view the active alarms. Correct the alarms and restart if necessary.
13. Press any button on the front panel display to activate the menu options, and then press the button until
the TURN UPS ON/OFF menu displays.
14. Press the
button to display the TURN UPS ON option; press the
button.
15. Confirm the selection. Press and hold the
button for three seconds, until the UPS stops beeping.
Verify that the
indicator illuminates solid, indicating that the UPS is operating normally and any
loads not connected through the load connector are now energized.
If the
indicator is flashing, do not proceed until all alarms are clear. Check the UPS status from the
front panel to view the active alarms. Correct the alarms and restart if necessary.
The UPS should be in Normal mode. By default, Normal mode operates on the High Efficiency setting ( see
section
”Operating Modes” ).
16. To energize a load connected through the load connector, switch the load connector circuit breaker to the
ON (|) position.
17. Press the
ESC
button until the Start screen appears.
18. If optional EBMs are installed, set the number of installed EBMs.
19. To change any other factory-set defaults see section
“Operation” ..
NOTE
Eaton recommends setting the Date and Time and the Start screen.
20. If you installed an optional REPO, test the REPO function:
Activate the external REPO switch. Verify the status change on the UPS display.
Deactivate the external REPO switch and restart the UPS.
21. See
.
NOTE
The batteries charge to 80% capacity in less than 5 hours. However, Eaton
recommends that the batteries charge for 48 hours after installation or long-term
storage.
Summary of Contents for BladeUPS none
Page 8: ...viii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Table of Contents ...
Page 12: ...xii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Figures ...
Page 14: ...xiv Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Tables ...
Page 20: ...6 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Introduction ...
Page 134: ...120 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Metering ...
Page 160: ...16420164914 164201649 14 ...