HyCassette-Geko
Hydraulic Connection
PR-2015-0159-GB • Subject to modifications • R1-11/2015
67
•
Insulate the condensate hose in the false ceiling to prevent condensation.
•
Ensure that the condensate hose is installed along the shortest path. Cut off
any surplus hose length
•
Do not install any grinds or waves, i.e. no local low points. Install the hose at
a constantly incline until the high point (see Fig. 5-17).
•
When laying out the pressure hose, ensure that it is not bent or folded. Insulate
the hose against all surfaces with which it could come into contact to prevent
the transmission of structure-borne noise.
NOTICE!
Maintain a continuous drain line pitch to provide adequate condensate drain-
age.
When connecting the condensate drain to the sewage system, observe the rel-
evant regulations of the local Water Board (stench trap).
Fig. 5-17: Hose at a constant incline