Electrical Connection
HyCassette-Geko
91
PR-2015-0159-GB • Subject to modifications • R1-11/2015
Pos. 1:
Internal safety fuse 6.3 A
Pos. 2:
Basic PCB power supply 230 V AC
ensure all-pole disconnect switch and fusing are provided on-site by others !
Pos. 3:
Alarm signals (contact 814-815 closed -> condensate pump fault)
Pos. 4:
Switch on electric heater with optional unit equipment
Pos. 5:
Fan control (terminal [pos. B/R] 801/1; = speed 1
802/2 = speed 2; 803/3 = speed 3) with
pos. B terminal block of the basic PCB for unit types without relay PCB
pos. R terminal block of relay PCB
Pos. 6:
Supporting terminal for valves
Pos. 7:
Terminals for exiting thermal contacts (optional)
In each case the sample connection of a miniature switch with 2 units is demon-
strated in the following wiring diagrams.
•
Connect only in accordance with the unit-specific wiring diagram.
Fig. 6-35: Terminal block basic PCB/relay PCB
1
2
3
6
4
5
7
Only terminals for
wiring control and
steering system
as well as supply
voltage are pre-
sented.
NOTICE!
Before starting with connections, check that the order code of the unit's electri-
cal equipment matches the wiring diagram. For units with external thermal con-
tact, the alarm signal can be tapped off. Refer to the unit connection diagram
for connecting terminals with error messages. According to the relevant regu-
lations, an all-pole isolating device must be provided by others on site.