6.
Slowly lower the cabinet onto the pad, keeping the mounting holes in the cabinet base
aligned with the anchor studs (or anchor holes) in the pad.
Note:
If properly aligned, the entry boxes in the splice compartment should slide down
over the conduits protruding up from the pad as the cabinet lowers. If necessary, reach
down through the entry boxes to grasp and align the top of the conduit to guide it
through the entry box. Do not reach under the cabinet.
7.
Pull the earth ground wire into the splice compartment through the center cable entry
box.
8.
After the cabinet rests on the pad, disconnect the slings from the cabinet lifting eyebolts.
9.
Anchor the cabinet to the pad as follows:
Pads with anchor studs:
a.
Get the six hex nuts, six square washers, and six lock washers from the
installation kit.
b.
Install one square washer, lock washer, and hex nut onto each of the six anchor
studs.
c.
Tighten the hex nuts to secure the cabinet to the pad.
Pre-cast pads with threaded inserts:
a.
Get six anchor bolts, six square washers, and six lock washers from the pre-cast
pad kit.
b.
Install one anchor bolt, square washer, and lock washer into each of the six
threaded mounting inserts.
c.
Tighten the bolts to secure the cabinet to the pad.