6-2
920011-649
Operator Manual
Routine Maintenance
6.2 Routine
Maintenance
Procedures included in this Routine Maintenance Guide should be
carried out only by operators who have received proper STERIS
training. Refer to appropriate sections containing detailed
instructions following this table for complete procedures.
Table 6-1. Routine Maintenance Guide
Recommended frequency of inspection is indicated in the right column. Usage and
utility conditions may require more or less frequent inspections.
Suggested
Frequency
1.0
PREPARATION FOR ROUTINE MAINTENANCE
When required by procedure, shut off all building services and drain all lines.
Always follow local occupational health and safety regulations, as well as electric
and plumbing codes.
As required
2.0
PRINTER
2.1
Verify for proper operation of printer. Verify printout for darkness, missing dots, etc.
Replace ribbon cartridge if necessary (see
S
ECTION
.
As required
2.2
Change printer paper roll (see
S
ECTION
).
As required
3.0
CHAMBER COMPONENTS
3.1
Verify debris screen in chamber is clean and in good condition. Replace if
necessary (see
S
ECTION
).
1 X/day
3.2
Perform a D-SHORT cycle (see
S
ECTION
).
Every 54 h
3.3
Clean chamber rotary spray arm assembly (see
S
ECTION
).
1 X/week
3.4
Perform a D-LONG cycle (see
S
ECTION
.
As required
3.5
Clean plastic surfaces and processor exterior panels (see
S
ECTION
).
1 X/week
3.6
Clean steel surfaces (see
S
ECTION
).
1 X/day
3.7
Clean drip pan strainer (
S
ECTION
.)
4 X/year
4.0
CLEANER INJECTION SYSTEM
4.1
Change Bag-in-a-Box container (see
S
ECTION
).
As required
4.2
Verify drip pan in bottom of Bag-in-a-Box compartment is clean and in good
condition. Replace if necessary (see
S
ECTION
).
1 X/week
5.0
ENDOSCOPE PROCESSING SUPPORT
5.1
Clean endoscope processing support rotary spray arm assembly (see
S
ECTION
).
1 X/week
5.2
Clean three draining holes at bottom of control handle boots using a thin wire
(such as a paper clip) or compressed air (see
S
ECTION
).
1 X/week
5.3
Clean draining holes in bottom of Reliance
TM
CDS Chemical Delivery System
using a thin wire (such as a paper clip) or compressed air (see
S
ECTION
).
1 X/week
5.4
Clean venting orifice of two Allen hex screws from Reliance CDS using
compressed air (see
S
ECTION
).
1 X/week
Содержание P920011-649
Страница 1: ...OPERATOR MANUAL Reliance EPS Endoscope Processing System 2022 03 10 P920011 649 ...
Страница 2: ......
Страница 13: ...xi 920011 649 Operator Manual Table of Contents ...
Страница 17: ...xiv 920011 649 Operator Manual List of Tables Healthcare Capital Equipment ...
Страница 25: ...1 8 920011 649 Operator Manual Safety Precautions Healthcare Capital Equipment ...
Страница 45: ...3 16 920011 649 Operator Manual Component Identification Healthcare Capital Equipment ...
Страница 167: ......
Страница 168: ...STERIS Corporation 5960 Heisley Road Mentor OH 44060 1834 USA 440 354 2600 800 548 4873 ...