Power Network Application Trainer
– Earth / Ground network impedance analysing
150
2. Connection diagram and parameter settings:
- connect the black test probe to H (C1) terminal and other part to the
“current probe”
R
CS
- connect the blue test probe to E(C2) terminal and other part to the
pylon
- connect the green test probe to the S (P1) terminal and other part to the
test probe (which will be used for simulation as voltage test probe)
- Prepare test point plan, as it is presented on the picture bellow:
Figure 88-2: Test point selection for GPR measurement
Setup test parameters
. Select the test frequency (range from
55Hz to 329Hz), Step Size and Direction.
Note: Step Size present index at which point measurement is done (number of
measurement).
Note: Since potential earth spike could not be used on the training module, Metrel
propose to use test probe.
Put the test probe on the first measurement point, labelled with n=0 and press START
key
on the instrument or icon
on the LCD:
Содержание MI 3298
Страница 55: ...Power Network Application Trainer Earthing Grounding network impedance measurement 55 ...
Страница 56: ...Power Network Application Trainer Earthing Grounding network impedance measurement 56 ...
Страница 124: ...Power Network Application Trainer Earthing Grounding network impedance measurement 124 ...
Страница 228: ...MI 3290 Earth Analyser 228 ...
Страница 229: ...MI 3280 Digital Transformer Analyser 229 ...
Страница 230: ...MI 3280 Digital Transformer Analyser 230 ...
Страница 231: ...MI 3250 MicroOhm 10A 231 ...
Страница 232: ...MI 3205 TeraOhmXA 5kV 232 ...