Maintenance
Maintenance plan
GE Information
08- 2016
L51- 004EN/07
5/8
Detail of maintenance operations
Caution
DURING MAINTENANCE OPERATIONS ALL POSSIBLE SAFETY
PRECAUTIONS SHOULD BE TAKEN TO PROTECT PERSONNEL
WORKING ON THE EQUIPMENT.
(Disconnect CB from HV system, remove LV supplies etc.)
General condition
of the apparatus
The apparatus should be subjected to visual inspection. If patches of
corrosion are found begin reconditioning of the affected parts.
The table below gives the process respecting surface finish and protection:
Support
Inspection
Action
Galvanized
steel
Oxidized parts
Thorough brushing of oxidized
parts.
Degreasing with solvent.
Application of a coat of zinc
paint.
Painted
galvanized
steel
or
painted
aluminium
alloy
Light scratches
Thorough degreasing with sol-
vent.
Application of a coat of lacquer
using a brush.
Deep scratches
or flaking
Scouring of paint surface with
emery paper 400.
Thorough degreasing with sol-
vent.
Application of a coat of primer,
then drying for 24 h.
Application of a coat of
polyurethane lacquer using a
brush.
Products used:
RUMCOAT EEVA primer by DERIVERY ref. 333103.
Polyurethane lacquer 780 by DERIVERY, ref. depending on color of equip-
ment.
Continued on next page.
Содержание SF6
Страница 2: ...Content Instruction Manual GE Information 04 2017 D1736EN 03 2 10 This page is intentionally blank...
Страница 50: ...Installation Tightening torques GE Information 07 2016 L31 001EN 03 4 4 This page is intentionally blank...
Страница 128: ...Installation Vacuum operation GE Information 08 2016 L31 881EN04 6 6 This page is intentionally blank...
Страница 176: ...Maintenance Maintenance plan GE Information 08 2016 L51 004EN 07 8 8 This page is intentionally blank...
Страница 178: ...Maintenance Electrical wear limits GE Information 08 2016 L51 052EN 05 2 2 This page is intentionally blank...
Страница 204: ...Annexes Tooling and accessories GE Information 08 2016 L60 028EN 04 8 8 This page is intentionally blank...
Страница 206: ...Grid Solutions This page is intentionally blank...
Страница 212: ...Grid Solutions This page is intentionally blank...
Страница 216: ...Grid Solutions This page is intentionally blank...
Страница 220: ...Grid Solutions This page is intentionally blank...
Страница 258: ...Installation Lifting and positioning the pole GE Information 08 2016 L31 200EN 07 4 4 This page is intentionally blank...
Страница 286: ...Installation Coupling of column and chambers GE Information L31 7138EN 02 16 16 11 2016 This page is intentionally blank...
Страница 299: ...GE Information This page is intentionally blank...
Страница 300: ......