Maintenance
Electrical contact densimeter threshold inspection
GE Information
08- 2016
L51- 108EN/06
2/8
Preparing the densimeter
Introduction
The densimeter is located at the base of the pole of the circuit- breaker, and
is joined to the SF
6
(or SF
6
+CF
4
) gas volume of the circuit- breaker.
To realize the electrical contact densimeter threshold inspection, it is imperat-
ive to isolate the densimeter volume from the pole SF
6
(or SF
6
+CF
4
) gas
volume.
Process
The table below gives the process to preparing the densimeter:
Step
Action
Diagram
1
Remove the densimeter
(1), held in place by
screws (8), on the hous-
ing cover (2) of the cir-
cuit- breaker.
x3
8
H M6-20
2
1
2
Remove the screws (14).
x3
14
H M6-20
3
Install the seal (16) on the
connection valve block
(5).
16
5
4
Install the connection
valve block (5) on the
housing cover (2), of the
circuit- breaker,
using
screws (8).
2
5
1
x3
14
H M6-20
0,7 daN.m
x3
8
H M6-20
0,7 daN.m
5
Install the densimeter (1)
on the connection valve
block (5) using screws
(14).
NOTE
: Before
installing,
check
the
presence of seals on
the densimeter.
Содержание SF6
Страница 2: ...Content Instruction Manual GE Information 04 2017 D1736EN 03 2 10 This page is intentionally blank...
Страница 50: ...Installation Tightening torques GE Information 07 2016 L31 001EN 03 4 4 This page is intentionally blank...
Страница 128: ...Installation Vacuum operation GE Information 08 2016 L31 881EN04 6 6 This page is intentionally blank...
Страница 176: ...Maintenance Maintenance plan GE Information 08 2016 L51 004EN 07 8 8 This page is intentionally blank...
Страница 178: ...Maintenance Electrical wear limits GE Information 08 2016 L51 052EN 05 2 2 This page is intentionally blank...
Страница 204: ...Annexes Tooling and accessories GE Information 08 2016 L60 028EN 04 8 8 This page is intentionally blank...
Страница 206: ...Grid Solutions This page is intentionally blank...
Страница 212: ...Grid Solutions This page is intentionally blank...
Страница 216: ...Grid Solutions This page is intentionally blank...
Страница 220: ...Grid Solutions This page is intentionally blank...
Страница 258: ...Installation Lifting and positioning the pole GE Information 08 2016 L31 200EN 07 4 4 This page is intentionally blank...
Страница 286: ...Installation Coupling of column and chambers GE Information L31 7138EN 02 16 16 11 2016 This page is intentionally blank...
Страница 299: ...GE Information This page is intentionally blank...
Страница 300: ......