GE Power Management
745 Transformer Management Relay
5-35
5 SETPOINTS
5.4 S2 SYSTEM SETUP
5
5.4.3 WINDING 1 (2/3)
These sections describe the characteristics of each transformer winding and the CTs connected to them.
The above setpoint options are also available for the second and third winding. W3 setpoints are only
visible if the unit has the appropriate hardware and if the selected transformer type is 3-winding.
y
WINDING 1
y
[ENTER] for more
This message indicates the start of the
WINDING 1 (2/3)
section. To continue
with these setpoints press
, or press
to go to the next
section.
WINDING 1 NOM ø-ø
VOLTAGE: 220.0 kV
Range: Above 5 kV - 0.1 to 2000.0 (steps of 0.1),
1 kV to 5 kV - 0.01 to 200.00 (steps of 0.01),
Below 1 kV - 0.001 to 20.000 (steps of 0.001)
Enter the nominal phase-to-phase voltage rating of Winding 1 (2/3) of the
transformer. The range for this setpoint is affected by the setting made at
S2 SYSTEM SETUP/TRANSFORMER/LOW VOLTAGE WINDING RATING
.
WINDING 1 RATED
LOAD: 100.0 MVA
Range: Above 5 kV - 0.1 to 2000.0 (steps of 0.1),
1 kV to 5 kV - 0.01 to 200.00 (steps of 0.01),
Below 1 kV - 0.001 to 20.000 (steps of 0.001)
Enter the self-cooled load rating for Winding 1 (2/3) of the transformer. The
range for this setpoint is affected by the setting made at
S2 SYSTEM SETUP/
TRANSFORMER/LOW VOLTAGE WINDING RATING
.
WINDING 1 PHASE CT
PRIMARY: 500:5 A
Range: 1 to 50000 (steps of 1)
Enter the phase CT primary current rating of the current transformers
connected to Winding 1 (2/3). The CT secondary current rating must match
the relay phase current input rating indicated.
WINDING 1 GROUND CT
PRIMARY: 500:5 A
Range: 1 to 50000 (steps of 1)
Enter the ground CT primary current rating of the current transformers
connected in the Winding 1 (2/3) neutral to ground path. The CT secondary
current rating must match the relay ground current input rating indicated.
This message will only appear if the transformer type setpoint shows that
Winding 1 (2/3) is a wye-connected winding.
WINDING 1 SERIES 3ø
RESISTANCE: 10.700 O
Range: 0.001 to 50.000 (steps of 0.001)
Enter the series three-phase resistance of the winding (i.e. the sum of the
resistance of each of the three phases for the winding). This value is
normally only available from the transformer manufacturer’s test report, and
is used in the 745 for calculation of harmonic derating factor.
E N T E R
M E SSA G E
NOTE
Содержание 745 TRANSFORMER MANAGEMENT RELAY
Страница 30: ...2 8 745 Transformer Management Relay GE Power Management 2 3 SECURITY 2 GETTING STARTED 2 ...
Страница 150: ...5 100 745 Transformer Management Relay GE Power Management 5 10 INVERSE VOLTS PER HERTZ CURVES 5 SETPOINTS 5 ...
Страница 210: ...7 36 745 Transformer Management Relay GE Power Management 7 2 BLOCK DIAGRAMS 7 SCHEME LOGIC 7 ...
Страница 322: ...9 12 745 Transformer Management Relay GE Power Management 9 3 USING 745PC 9 745 PC SOFTWARE 9 ...
Страница 392: ...11 24 745 Transformer Management Relay GE Power Management 11 1 COMMISSIONING SUMMARY 11 SETPOINT TABLES 11 ...
Страница 396: ...A 4 745 Transformer Management Relay GE Power Management A 1 FIGURES AND TABLES APPENDIXA A ...
Страница 398: ...B 2 745 Transformer Management Relay GE Power Management B 1 EU DECLARATION OF CONFORMITY APPENDIXB B ...
Страница 400: ...C 2 745 Transformer Management Relay GE Power Management C 1 WARRANTY INFORMATION APPENDIXC C ...
Страница 406: ...vi 745 Transformer Management Relay GE Power Management ...
Страница 407: ...GE Power Management 745 Transformer Management Relay NOTES ...