13.2.3
Installation of Meter on Bench
1.
Install the meter on the prover table, and adjust the meter arms to fit the appropriate height and
width of the meter.
On the SNAP prover, extensions are required for the meter connections because of the shorter height
of the meter.
Use the connections according to the ones installed on the meter. For example, if the meter uses 45LT
connections, use the 45LT swivels on the prover.
2.
Install the IrDA test cable from the prover to the meter. Slide the black box into the adapter for the
IrDA slot on the bottom of the digital index.
3.
After the cable is connected to the meter, connect the other end to the optical outlet port (J4) on the
prover. This port is a keyed 9-pin connector that can only be installed in one orientation.
Figure 68: Optical sensor port (J4) with connector
Figure 69: J4 port without connector
Note:
If you set up the 10C25 meter text and exited, the
METER
area in the center of the
screen displays the test is for the 10C25. If you tested another meter before testing the
10C25, click
SELECT METER TYPE
, click the
OTHER
button, click
10C25
, and then click
EXIT
.
The
METER
area should display
10C25
.