f-Protection Module – Frequency Protection [ANSI 81O/U]
Commissioning: Frequency Protection (Overfrequency) [ANSI 81O]
Object to be tested
All parameterized overfrequency protection stages.
Necessary means
•
Three-phase voltage source with variable frequency.
•
Timer
Procedure
Testing the threshold values
•
Keep on increasing the frequency until the respective frequency element is activated
•
Note the frequency value.
•
Disconnect the test voltage.
Testing the trip delay
•
Set the test voltage to nominal frequency.
•
Now connect a frequency jump (activation value) and then start a timer. Measure the tripping time at the
relay output.
Testing the fallback ratio
Reduce the measuring quantity to less than 99.95% of the trip value (or 0.05% fn). The relay must only fall back
at 99.95% of the trip value at the earliest (or 0.05% fn).
Successful test result
Permissible deviations/tolerances can be taken from the Technical Data.
Commissioning: Frequency Protection (Underfrequency) [ANSI 81U]
For all parameterized underfrequency elements, this test can be carried out similar to the test for overfrequency
protection (by using the related underfrequency values).
Please consider the following deviations:
•
For testing the threshold values the frequency has to be decreased until the protection element is
activated.
•
For detection of the fallback ratio the measuring quantity has to be increased to more than 100.05% of
the trip value (or 0.05% fn). At 100.05% of the trip value the relay is to fall back at the earliest
(or 0.05% fn).
Page 412
EN MRA4 04/09
Summary of Contents for SEG HighPROTEC MRA4
Page 1: ...MRA4 HighPROTEC Feeder Protection Device Manual DOK HB MRA4E...
Page 3: ...Order Code EN MRA4 04 09 Page 3...
Page 59: ...Navigation Operation Navigation Operation EN MRA4 04 09 Page 59 1 4 2 3 5 7 6 8 9...
Page 378: ...PQS Power Protection Module ANSI 32 37 Page 378 EN MRA4 04 09 P P Q P Q P Q Q Q P S S...
Page 379: ...PQS Power Protection Module ANSI 32 37 EN MRA4 04 09 Page 379 Pr Q P Q P Qr...