5.1 Opening and closing of the Sunny Boy
Normally the Sunny Boy operates fully automatically and maintenance-free. Should
the device nonetheless be opened e.g. for
•
upgrading or modification of the Sunny Boy interface
•
control of internal fuse
•
analysis of earth fault indication
•
setting up the input voltage range
follow the instructions given below.
Opening of the Sunny Boy
The Sunny Boy must only be opened by a qualified electrician.
When working on the Sunny Boy follow the instructions below:
1. Separate the Sunny Boy from the grid by opening the circuit breaker.
2. Separate all poles of the Sunny Boy from the PV-panel by pulling the MC plug
connectors.
Wait for approx. 5 minutes until internal voltage has discharged.
3. Open the Sunny Boy in the following order.
4. Take off the lid by removing screws 1-4 (see Fig. 5.2 on page 47) on the lid (M5).