Sunny Boy 700
Technical Description
SB700-11:EE
-
22
-
SMA Regelsysteme GmbH
3.3 Electric Connection
The electric connection of the Sunny Boy can be done once the device is correctly
mounted in its position.
The grid and the input from the PV-modules are connected to the inverter in the bot-
tom of the case. The connection is done with special plug connectors (see Fig. 5.3
on page 48).
The connection of the Sunny Boy to the DC voltage from the PV
string and the AC voltage of the utility must be done in the order de-
scribed here. This ensures that the disconnecting of contacts as well
as hazardous voltages during the installation are avoided.
1. Connect to the electricity grid (see chapter 3.3.1).
2. Connect the PV string (see chapter 3.3.2).
3. Connect the PV string to the Sunny Boy.
4. Connect the utility by putting the AC fuse on.
Disconnecting the Sunny Boy must be done in the opposite order:
1. Disconnect the inverter from the grid (automatic circuit breaker “OFF”)
2. Disconnect the PV panel from the Sunny Boy (pull the MC plugs)
3. Remove the AC connector from the Sunny Boy