Note: it is recommended to install the unit as high as possible
ATTENTION!
Don’t install electrical box/electrical device below the air
conditioner
Installation of air conditioner
ATTENTION!
Disconnect the power supply of the cabinet before carrying out
any work on the cabinet
External installation:
a. Make the holes in according the cut-out
b. Unpacking the unit as described on chapter 4 and take out unit
from packaging with n.2 eyebolts (M6/M8)
c. Apply gasket (supply by STULZ SpA) on rear of unit so that no gaps
are left at connection points (more informations on cap.16)
d. Fix the unit to cabinet with screws
Semi-flush installation (codes CVE0700S, CVE1500S, CVE2500S):
-
Make the holes in according the cut-out
-
Unpacking the unit as described on chapter 4 and take out unit
from packaging with n.2 eyebolts (M6/M8)
-
Remove the panel unscrewing screws (1 and 2)
cable of display
-
Remove the plate of condenser fan unscrewing screws
remove the condenser fan (disconnecting the connector of the fan)
-
Disconnecting the ground cable to front frame of the air
conditioner
-
Unscrew screws and remove the front frame of the air
conditioner
-
Unscrew spacer bolts
-
Apply gasket (supply by STULZ SpA) along the
frame so that no gaps are left at connection points
informations on cap.16)
-
Fix the unit using spacer bolts (previously removed)
-
Re-connect the ground cable and put in the front frame and fix
it
27
stall the unit as high as possible
Don’t install electrical box/electrical device below the air
Disconnect the power supply of the cabinet before carrying out
b. Unpacking the unit as described on chapter 4 and take out unit
on rear of unit so that no gaps
at connection points (more informations on cap.16)
flush installation (codes CVE0700S, CVE1500S, CVE2500S):
Unpacking the unit as described on chapter 4 and take out unit
Remove the panel unscrewing screws (1 and 2) and disconnect
Remove the plate of condenser fan unscrewing screws and
(disconnecting the connector of the fan)
Disconnecting the ground cable to front frame of the air
and remove the front frame of the air
) along the inside of the rear
frame so that no gaps are left at connection points (more
Fix the unit using spacer bolts (previously removed)
connect the ground cable and put in the front frame and fix
-
Re-connect the connector of condens
condenser fan and fix the condenser fan plate
-
Re-connect the cable of display and fix the panel
Note: to make easy the positioning of air conditioner there are 2 male
threaded pin, and 2 nuts, to put on higher insert of
standard screws in order to hang the unit on first mounting activity.
WARNING: The unit must be handled using the appropriate lifting
devices inserting the eyebolts (M6/M8
Installation with semi-encasing frame/total
-
Make the holes in according the cut
frame/total-encasing frame
-
Put semi-encasing frame on cut
-
Remove protection rubber from insert of frame
-
Apply gasket (supply by STULZ SpA
total-encasing frame
-
Fix semi-encasing frame with washers and nuts (supply by
STULZ SpA
-
If necessary to cut the condensate drain tube in order to avoid
bend, it is recommended a diagonal cut
-
Carry out operation as described on paragraph “External
installation” for installation of air conditioner (points b., c., d.)
ATTENTION
Do not obstruct the circulation of supply/intake air by air
conditioner
Discharge of condensate water
It has to be orientated downward, it has to lay without bending, in
case it is necessary to increase length the diameter has not be
reduced .
Electrical connection
ATTENTION
Work on the unit can only be carried out by qualified authorized
personnel
CVE-CVO
connect the connector of condenser fan, put in the
condenser fan and fix the condenser fan plate
connect the cable of display and fix the panel
Note: to make easy the positioning of air conditioner there are 2 male
threaded pin, and 2 nuts, to put on higher insert of frame, over
standard screws in order to hang the unit on first mounting activity.
The unit must be handled using the appropriate lifting
M6/M8) in the prearranged holes.
encasing frame/total-encasing frame
Make the holes in according the cut-out of semi-encasing
encasing frame
encasing frame on cut-out
Remove protection rubber from insert of frame
STULZ SpA) on semi-encasing frame/
encasing frame with washers and nuts (supply by
If necessary to cut the condensate drain tube in order to avoid
bend, it is recommended a diagonal cut
Carry out operation as described on paragraph “External
installation of air conditioner (points b., c., d.)
ATTENTION!
Do not obstruct the circulation of supply/intake air by air
conditioner
It has to be orientated downward, it has to lay without bending, in
necessary to increase length the diameter has not be
ATTENTION!
Work on the unit can only be carried out by qualified authorized
personnel
1
2
Summary of Contents for Cosmotec CVE Series
Page 2: ......
Page 3: ...CVE CVO 3...
Page 4: ...CVE CVO 4...
Page 83: ...CVE CVO 83...
Page 84: ...CVE CVO 84...
Page 88: ......