4.2.3
Installation
Procedure
Having dismantled the SINAMICS G110M Terminal Housing, the following procedure should be
performed to complete the installation of the whole system.
1. Star and Delta Configuration
Configure the motor terminals for either star or delta configura‐
tion depending upon the voltage requirement of the application
and the mains input voltage.
2. Fit the earth cable to the motor
1. Secure the earth cable to the motor terminal box.
2. Ensure that the cable is facing in the correct direction to allow
connection to the earthing post on the Terminal Housing.
Note:
• The earthing cable is supplied with the Terminal Housing.
• On the FS80/90 Terminal Housings there are two additional
fixing points which are the earthing points between the Ter‐
minal Housing and the motor. These earthing points must be
used and therefore, the earthing cable does not need to be
fitted.
• If the SINAMICS G110M is ordered as a complete system,
then all mechanical and electrical installation is completed in
the factory prior to delivery.
Installation
4.2 System Installation
Distributed converter for SIMOGEAR geared motors
46
Operating Instructions, 10/2020, FW V4.7 SP13, A5E31298649B AL