Site Survey
4 - 2 • • • Intelli-FLEX II product guide
Site Survey
A survey should be conducted before installing any system hardware to ensure
that the site conditions are suitable for optimum function of an Intelli-FLEX II
system. The primary concern of the site survey is the condition of the fences and
gates where the sensor cable will be attached.
When conducting the site survey indicate the following on the site plan:
•
locations of existing structures (include fences, gates, buildings, etc.) Check
that the mounting surfaces are in compliance with established standards with
respect to stability.
•
location of obstacles such as vegetation.
Figure 4-1 Sample site plan
Z1
Z2
Z3
Z4
Z5
Z6
Z7
Z8
Z9
proc #4
proc #1
proc #2
proc #3
terminator (typical)
sally port gate
(included in Z6)
microwave
sensors
main
building
swinging gate
(included in Z3)
NOTE:
not required
gate disconnect
- extra sensor cable at corner poles
service
loops
- drip loops at each splice/termination
sally port
gate
end of zone overlap
(approx. 1.5 m (5 ft.))
Also required at start points
max 290 m (950 ft.)
non-sensitive feed cable
(typical)
- service loops
gate disconnect