PASCA_TOUCHIT_EN
V02 | 07.2013
99
System
Water drainage
The "Water drainage" system parameter is used to cool the water system of the machine. In
addition, the machine is depressurised if the correct order was maintained.
►
Select the "Test / calibration" system parameter.
►
Select the "Water drainage" submenu.
The message for starting or cancelling the water drainage appears.
Option 1: Activating water drainage
►
Replace the milk container with the cleaning container before starting the "Water drainage"
procedure.
►
Select the [OK] field.
Drainage (flooding) starts with a countdown starting at 4 min.
After 2 min., the [OK] field appears to make it possible to prematurely cancel the pro-
cedure.
►
Wait until the water pump was activated during the process for approx. ca. 10 sec.
Water flows out at the steam wand and beverage outlet.
37) M11 PWMtopping right
Right powder dosing of topping.
►
Enter the powder dosing.
►
Confirm the entry.
The dosing runs with the set speed.
►
Change the set value back to "0".
The dosing is switched off.
0-100
"0"= switched off.
"100"= max. Dosierung.
38) M12 PWM top.standard
Standard powder dosing of topping.
►
Enter the powder dosing.
►
Confirm the entry.
The dosing runs with the set speed.
►
Change the set value back to "0".
The dosing is switched off.
0-100
"0"= switched off.
"100"= max. Dosierung.
The name of the "Water drainage" system parameter is misleading because this parameter,
which is described below, is not used to drain the water system. To actually drain the water
from the entire system, Schaerer technical support must be contacted.
Parameters: Output test
Display text
Description
Setting range
Notes
See "Programming" - "Access".
For the water system to be depressurised after the procedure, the [OK] field must not be se-
lected.